10
degrees at 7am. So stayed in bed till 8. Lovely blue sky and the sun is slowly
warming us up. More boats pulling up for a fish. We drove along the edge of the
lagoon, more day use areas with guys wadding or in a boat fishing. Passed the
end dam wall, will check that out on the way back. Further down the trees
cleared for a fantastic view over forestry land and down into the valley to the
Waddamana Power Station.
Heading
down a narrow dirt road, glad we don’t have the van on. It says on the brochure, caravan and camper friendly!!
We
were at 930m altitude at our camp and we have dropped quickly to 600m. As we
drive in the original houses are still there and are now the Field Study
offices and holiday accommodation, owned by a private organisation.
Big
grid towers and lines cover a lot of land.
Looking
at the Museum that was once Waddamana Power Station A. There is another
building on the other side called B. We have a self-guide tour brochure from
the Info Centre in Deloraine.
Another
grid area closer to the power station.
Looking
back up the hill.
Lovely
trees.
The
water pipes coming down the hill into the power station. These come from
Penstock Lagoon but of course aren’t in use anymore.
Information
about the two stations.
Paintings
of Princess Elizabeth (before she became Queen) and her father King George VI
were done by a polish ex-serviceman working at the power station.
A
rainbow trout – actual size – what a tubby. A lot bigger than the ones we have
seen.
This
building and all its equipment etc have been turned into a museum and it is
free. This is the info from the brochure etc and I have added the photos from
the museum.
The
harnessing of the waters of Great Lake began in 1910when a private company
started work on an ambitious project to divert water from Great Lake and the
Shannon River to a power station at Waddamana. In 1905 Professor Alex McAulay
published an article on the potential for hydro-electric power generation in
Tasmania. Mr Gillies, who had developed a new electrolytic metal refining
process was seeking a large, cheap power source. After reading the article, Mr
Brettingham-Moore who was a civil engineer, arranged a meeting with Mr Gillies.
They formed the Complex Ores Company in 1908 and sought finance for the power
scheme from the Tasmanian Government. The Government could not afford the
venture. In 1909 the Government granted a concession to the company to use the
water of Great Lake to produce electricity. A separate, smaller company called
the Hydro-Electric Power and Metallurgical Co. Ltd was formed to build the
scheme. They went back to England to raise the 145,000 pounds needed. Work
began on the scheme in Dec 1910 with the excavation of the canal which was to
convey water from Great Lake to the Penstock Lagoon. Because of considerable
difficulties during the early states and an extremely severe winter in 1912,
the company ran short of money and work halted for several months. The company
was unable to raise the extra money needed to continue construction. In 1914,
the Tasmanian Government bought the hydro-electric assets from the struggling
company. The Hydro-Electric Department was formed to manage the completion of
the scheme and went on to become Hydro Tasmania as we know it today. The water
came down from Miena where a small dam was erected between 1910 and 1916 across
the Shannon River (that we saw yesterday) and canals and pipelines brought the
water down.
Miena
No. 1 dam
The
first two generators came into service in May 1916 providing the first
hydro-electric power to Hobart. Between 1918 and 1923 there was an increased
demand for electricity. Waddamana A station was enlarged to accommodate a
further seven generators. To increase the supply of water a multiple arch
concrete dam was built in 1922 behind the original one at Miena to raise the
level of Great Lake.
Miena
No. 2 dam
The
upper reaches of the Ouse River were diverted (through Lake Augusta’s Dam) into
Great Lake by a flume and canal to provide further water.
The
Shannon Power Station began operation in 1931, it used the fall of water
between Great Lake and Waddamana. This is the original control room electrical
switchboard. It was transported to Waddamana after Shannon was decommissioned
in 1964.
Between
1939 and 1949 a second power station was constructed at Waddamana. Waddamana B
was built at right angles to the original Waddamana A power station and it
contained four turbines. These three power stations operating together between
1949 and 1964, had a total generating capacity of 107.5 megawatts. Waddamana A
and Shannon were decommissioned in 1965, Waddamana B operated until 1995. In
1965 the water stored in Great Lake is now used at Poatina Power Station
located to the north (after they dug a 6km tunnel through north end of the
Great Western Tiers). The sheer drop of the Great Western Tiers makes Poatina a
more efficient station. In 1967 another dam wall was added behind the existing
two at Miena to increase the water storage of Great Lake. Then in 1982 more rockfill was added to again
increase the storage capacity of Great Lake.
It
is very interesting and there was heaps to look at. It is amazing what they
achieved in those days with just plain hard work, no modern machinery they have
now. We watched a video of which they even had some videos of early 1900s and
lots of photos. There was no road link to the construction site. Early in 1911
work began on building a 27kmwooden tramway from Red Gate near Bothwell to
Waddamana. The tramway was completed in early 1912. Teams of up to 15 draught
horses pulled each load; the average load was about 7 tons. Truly amazing.
A
road was completed in 1922 and the tramway fell into disrepair. Advertisements
for labour made it quite clear that applications should make their own way to
the construction site which was described as a comfortable two day walk from
Deloraine. Rates of pay were 8/- (80cents) a day and a tent and sack of straw
to sleep on were provided!!! Yeah!!!
Power
Station Office – the office belonged to the power station superintendent. It is
in original condition and features models in period costume and original office
furniture and equipment, papers and power station plan. Also on display is the
original telephone switchboard and the old safe.
Next
door is the Engineers Office.
We
walked out into a verandah type thing to overlook the power station turbines.
Some old maps and books etc on display.
Walked
down onto the main floor, looking up at the lovely timber work of the verandah
room.
A
note on the door says to keep them closed to keep out the birds – obviously a
pair have gotten in here.
Lots
of great old photos. The original power station. The work was hard excavating
the foundations etc.
Living
conditions must have been bad in the beginning.
They
kept the turbines running while they added on the extension.
After
the extensions to add the next 7 turbine generators. It was a real community by
then. The water flowed out (to the top of the photo) to join the Ouse River.
The
mail coach even made it through during winter.
Two
great panorama photos – the power station site and Great Lake
All
the tools are still hanging in the tool storeroom. Most were handmade due to
the isolation of the power station.
Looking
down over the 9 turbine generators.
They
have one open so you can see how it works. In 1831 it was discovered that
electricity could be produced by rotating an electro-magnet inside coils of
wire. The alternators in large power stations work on the same principle. In
hydro power stations, water is used to make the electro-magnets spin. At
Waddamana, Pelton wheels were used to tap the energy of the moving water. These
wheels spin a shaft which is connected to the electro-magnets, which in turn
spin around inside the coils of conductor. This generating process converts the
mechanical energy of the Pelton wheel into electrical energy.
Turbine
Magnetic Alternator
At
Waddamana A two engines were initially installed. Each had a capacity of 4900
horse power (3.65megawatts), enough electricity to supply about 250 to 300
homes. They came into operation in 1916, at that time there were about 2000
customers in the Hobart area. Ad additional machine was operating by 1919. A
further six 8000HP (5.96MW) machines were installed after 1922. An old photo of
7 machines in operation.
Around
the building are lots of interesting displays. This shows the layout of the power station.
As
steel was hard to get in the war years the pipes were made of wood with steel
bands around them, called Woodstave Pipes. The original pipeline was
constructed of Oregon pine. A later wooden pipeline was constructed from kauri
and jarrah, imported from Western Australia. Woodstave pipelines are still in
use at Lake Margaret Power Station on the west coast of Tasmania and elsewhere.
A
closer look through the floor where the inlet pipes come in, the turbine and
the generator.
Electric
rivet heater – interesting, how would that have worked on the Sydney Harbour
Bridge.
DC
Exciters made in England by GEC (General Electric Co).
Steve
liked the “heavy lifting” poster.
Went
into the corridor that joins A & B buildings. Look out onto the inlet pipes
and up the hillside.
The
other side shows more pipes going in to feed the other generators. Each
generator had its own pipe of water.
Waddamana
B power plant – we didn’t have access to these.
Lots
of transformers on display. Transformers are used to increase the electricity
voltage produced in the power station for transporting over the transmission
lines then decrease to low voltage before being distributed to consumers.
There
were interactive displays to teach the kids (and us) about electricity etc. One
was four plates, two aluminium and two copper. Put your hands on them and watch
the current flow through your body etc. Very interesting. Steve learning how the water turbine works!!
Played
with the plasma ball.
The
Alternating Current Generator was from USA but the big turbines were from
England.
The
stairs were blocked off, presumably to the pipework below. The breeze coming up
though was freezing. Would have been terrible in winter time.
There
were displays of old stoves, appliances, heaters, power meters, light bulbs,
anything to do with electricity.
An
envelope sealer!!! And other office equipment.
This
looks a good heater with a fan too.
The
control room is the heart of a power station. All required changes and
alternations to the daily running of the station were made from here. Major
events occurring in the power station are recorded by control room staff on the
daily log. The control room was used to control the power supply from both
Waddamana A and B stations. The marble panels used for Waddamana A are a
feature. The marble was used for its insulating qualities. An air raid siren
was also installed during World War 2.
The
power station workshop was used for maintaining machines and equipment. The
workshop houses a metal lathe (manufactured in Melbourne), the bed of which was
specially adapted to turn extra long shafts.
Major conveyor belt system to turn the lathe.
Walked
around the building to look at the Waddamana B building.
And
down the canal that used to take the water away, from the power station after
it had been through the turbines, and back into Ouse River.
The
old street lamps still exist too.
Drove
past some of the old homes, still loving cared for. These are the Field
Offices.
These
pine trees were huge and their pine cones were enormous.
Back
up the road and passed all the lovely yellow flowered bushes.
The
sun has disappeared unfortunately making it cool again. Stopped at the southern
dam wall of Penstock Lagoon and climbed up for a look.
There
were a few people out in boats and a chap on the dam wall.
We
timed it perfectly as he had just hooked a trout. Watched him bring it in and
then asked if I could take a photo. This one is going home for dinner.
It
is a brown trout and check out the size of the fly.
Looking
back on the bund wall dam (Steve told me that name) and log diverter.
The
water used to flow down these old pipes and down to the power station.
Now
there is just a dribble coming out of a crack in the wall – maybe I should put
my finger in the dyke!!
Looking
back at the outlet pipe under the dam wall area.
Made
lunch – Steve into open grill sandwiches now – trying to cut down on the double
toasted sandwiches he was having. I had omelette – yum. Started working on
today’s photos – lots but very interesting. Made some yummy scones for smoko
then decided to made some muffins and a cake as it was spitting with rain
outside.
Steve
went for a walk to check out the fisherman. The chap from Lake Ada has arrived
but he hasn’t caught one yet. They are all still waiting for the Rise. Before
the Shannon River had its course changed with the dam, it used to be
world-famous for the trout. Anglers fished shoulder-to-shoulder. The Shannon
Moth, a snowflake caddis, used to hatch in early summer, causing trout to
“rise” eagerly for a feed.
Quiet
night, even the birds are quiet, as it is overcast and cool. Steve had got the
fire already but the drops of rain kept plopping so we had dinner in the van.
Tried to use the phone but our reception has lessened with the cloud cover. Put
out the vegie scraps for the possum. We played a few games of Sequence and
about 10pm the possum arrived for dinner. Another one turned up so I chopped up
another carrot for him/her.
No comments:
Post a Comment